Single contract of construction of sewage treatment plant including operation & maintenance thereof for 15 years
Facts of the Case
- Uttarakhand Peyjal Nigam issued a tender in December 2017 for the project ‘construction of sewage treatment plant including operation & maintenance thereof for 15 years’.
- The petitioner submitted the bid as under:
- Construction: Rs. 72.43 Crores
- O&M: Rs. 53.94 Crores
- The petitioner completed construction phase and begun the O&M phase.
- As per Not. No. 12/2012 CT (Rate), “composite supply of goods and services in which the value of goods constitutes not more than 25% of the value of said composite supply provided to the CG or SG or UT or local authority or a Governmental authority or a Government Entity by way of an activity in relation to any function entrusted to a Panchayat under article 243G of the Constitution or in relation to any function entrusted to a Municipality under article 243W of the Constitution” is fully exempt from levy of tax.
- Accordingly, an Advance Ruling was filed before AAR on the question whether O&M service is exempt from tax?
- The AAR answered in negative and held as under:
- O&M is part of same supplies.
- Construction is a principal supply.
- O&M is a supplementary supply which is secondary to construction
- Bifurcation of goods and services provided by petitioner is not reliable
- Petitioner has tried to split the contract and shown the value of O&M only to avoid GST liability
- Full value of contract attracts GST
- There is neither separate contract nor separate schedule for payment of O&M services
- If the total value of contract is taken into consideration, the value of goods cannot be justified below 25%.
- On an appeal filed before AAR-Appeals, the ruling of AAR was upheld with following observations:
i. There was a single E-Bid
ii. O&M is an intrinsic part of the main contract
iii. The word “including” has been used between construction and O&M
iv. O&M cannot be an independent activity
v. No separate exclusive contract has been made for O&M
vi. O&M is an ancillary supply
Our Analysis
- Bid Price was separate for each activity
- Performance Security is separate for each activity
- Separate consideration has been agreed for each work
- Separate schedules are incorporated in contract for each work
- Payment schedules are separate in contract for each work
- Contract period is contractually defined as “Construction period” and “O&M period”
- There are independent clauses for liquidated damages
- At the time of discussion on issuance of exemption notification, O&M activity of the water purification projects was also discussed in examples put forth before GST Council
- Hon’ble Supreme Court has already upheld that a single document can have two separate and distinct contracts.
- On completion of construction, a commissioning certificate is issued. That is the end of construction period. The O&M for duration of 15 years after the commissioning is entirely independent of the first part and at no rate can be considered to be ancillary.
- From the economic point of view of customer, O&M do have its independent utility, and must be considered as separate and distinct to construction.
- AAR-Appeal exceeded the jurisdiction by pronouncing ruling on the entire contract.
Action taken
- A writ petition was filed before Hon’ble Uttarakhand High Court at Nainital.
- The court admitted the writ petition and issued notice to the respondents among other directions.